Tender Number: MWP2518TX
Description: The Contractor is required to complete Engineering, Procurement and Construction of the third 500MVA 400/132/22kV Transformer at Mercury MTS in the Eskom Transmission Grid and comprises:
Place where services required: THE TENDER OFFICE Eskom Megawatt Park - Tender office North Side Maxwell Drive Sunninghill 2157
Special conditions: All Suppliers
Date Published: 2024-04-26T13:27:01
Closing Date: 2024-07-16T10:00:00
Enquires
Contact Person:
Contact Email: mashite.mabilo@eskom.co.za
Briefing Session
Is there a briefing session: Yes
Is it compulsory: NO
Briefing Date and Time: 2024-05-16T10:00:00
Briefing Venue: MS Teams
Document Links
- 240-56030674 Corrosion protection and maintenance of new and in service trfrs and rxs.pdf
- 240-56062720 Oil sampling points labels.pdf
- 240-56063843 Analogue oil and winding temperature indicators.pdf
- 240-56063871 Pressure relief devices.pdf
- 240-56063908 OIl and gas actuated relays (buchholz).pdf
- 240-56356191 Transformer and reactor oil level indicator.pdf
- 240-75661431 Rev 2 _STANDARD FOR MINERAL INSULATING OILS_NOV 2020 (00.._.pdf
- 315 kVA 22kV-400V Auxiliary Transformer.xlsx
- Passive Dehydrating Breathers 240-56062529.pdf
- ST_240-57648800 Standard - New oil filled auxiliary transformers - Rev 3.pdf
- ST_24077155912 TECHNICAL TENDER EVALUATION CRITERIA FOR AUXILIARY TRANSFORMERS AND NECRTS Rev 4s (002).pdf
- Concept Design Report Rev01 Mer23P13-SE-C12.pdf
- Mer23P13-SE-C3.dgn
- Mer23P13-SE-C4.dgn
- 0-WT-51-0.dgn
- 0-WT-109-1A.dgn
- 0-WT-109-2.dgn
- 0-WT-109-2A.dgn
- 0-WT-109-2B.dgn
- 0-WT-109-7.dgn
- 0-WT-109-11.dgn
- 0-WT-109-13.dgn
- 0-WT-109-14.dgn
- 0-WT-109-14A.dgn
- 0-WT-109-15.dgn
- 0-WT-109-35.dgn
- 0-WT-109-39.dgn
- 0-WT-109-40.dgn
- 0-WT-109-43.dgn
- 0-WT-109-43A.dgn
- 0-WT-109-44.dgn
- 0-WT-109-44A.dgn
- 0-WT-110-0.dgn
- 0-WT-110-1.dgn
- 0-WT-111-0.dgn
- 0-WT-112-0.dgn
- 0-WT-113-0.dgn
- 0-WT-114-0.dgn
- 0-WT-132-0.dgn
- 0-WT-133-0.tif
- 0-WT-134-0_0.tif
- 0-WT-146-0.tif
- 0-WT-147-0.tif
- 0-WT-148-0.tif
- 0-WT-149-0.tif
- 0-WT-150-0.dgn
- 0-WT-150-1.dgn
- 0-WT-150-2.dgn
- 0-WT-494-0.dgn
- 0-WT-514-1.dgn
- 0-WT-514-2.dgn
- 0-WT-514-3.dgn
- 0-WT-522.dgn
- 0-WT-902.dgn
- 240-171000161 Technical Evaluation Standard for Substation Stranded Conductor Clamps _ EPC Contracting.pdf
- 240-171000165 - Technical Evaluation Standard for the Stringing Earthing and Erection at Transmission Substations.pdf
- Stringing earthing and erection Technical Evaluation criteria - Scoring1.xlsx
- Transmission Substation Engineering Functional Parameters - (Full EPC) Rev 1 Signed.pdf
- 22kV Label 240-68160276.xls
- 132kV Label 240-68160308.xls
- 400kV Label 240-68160368.xls
- Combined proformas.xlsm
- Mercury 3rd Transformer project - TRFR proforma RR.pdf
- Mercury 3rd Transformwer project - TRFR proforma.pdf
- Mercury 3rd Transformwer project - TRFR proformer.pdf
- Mercury 3rd Transformwer project - TRFR proformer.xlsm
- Proforma LOngrod insulator.xls
- Safety labels.doc
- 240-170001091-Mercury 3rd Trfr High Level Scope of Work - PTMC Equipment_Rev1-signed.pdf
- 240-180000669 Mercury 3rdTrfr PC Cabling Rev 2_VN.pdf
- 240-180000670 EPC PTMC Mercury Technical Evaluation Criteria Document-signed.pdf
- Mercury SS PTMC Concept Design Report.pdf
- 01.QITP's. HVT. Earth Wire and Tubular Installation.Ferrum. Apr. 2016.pdf
- 20110928_Spitskop Q ITP Cabling Stringing Earthing.pdf
- Actom Earthing QITP.pdf
- Civil Qitp.pdf
- Earthing QCP - Ngwedi - Contract - 4600051731.pdf
- Erection QCP - Ngwedi - Contract - 4600051731.pdf
- Example-Cabling_1.pdf
- Example-EarthingOfStructures_1.pdf
- Example-Earthworks.pdf
- Example-EquipmentFoundations.pdf
- Example-Erection_1.pdf
- Example-Stringing_1.pdf
- Example-TerminationOfJBs.pdf
- Matimba Bases and Plinths ITP 30012014.pdf
- Mercury_Scope of work_EPC_Basic_Rev1 RR CT AM NP.pdf
- 240-56177186 Battery Room Standard.pdf
- 240-76368574 High Risk Security Mesh Fencing.pdf
- 240-82172806 Standard for Air Conditioning In Transmission Substation Buildings and Telecommunication Sites.pdf
- 240-83382076 Standard for the Operations Floodlighting in Transmission Substations.pdf
- 240-83382122 Emergency Lighting in Transmission Substations.pdf
- 240-94743192 Standard For Fabrication Steelwork Used In Eskom Transmission Substations.pdf
- 240-94743194 Standard For The Erection Of Steelwork And Microwave Towers In Eskom Transmission Substations.pdf
- 240-98161024 Standard for Rock Blasting In Substations.pdf
- 240-100183119 Standard for the Substation HV Yard Fences.pdf
- 240-101811486 Standard for Crusher Plant.pdf
- 240-102384426 Standard For Substation Surveys.pdf
- 240-102393009 Standard For Substation Flood Analysis Design.pdf
- 240-108982466 Standard For Yardstone In Eskom Substations.pdf
- 240-153000199 Substations Drainage Specification.pdf
- Application Guide.pdf
- 32-727 Safety, Health, Environment, and Quality (SHEQ) Policy.pdf
- 32-1205 Eskom Maintenance Management Policy.pdf
- 240-4620188 TERMS OF REFERENCE FOR DESIGN REVIEW TEAMS PRESIDING OVER TRANSMISSION AND DISTRIBUTION INFRASTRUCTURE DESIGNS IN ESKOM.pdf
- 240-8752999 A Study On the Design Philosophy For 500kV Tubular Conductor Busbar Yards.pdf
- 240-53113923 Specification for Substation Clamps for Tube Aluminium Conductors.pdf
- 240-53113927 Specification for Substation Clamps for Stranded Aluminium Conductors.pdf
- 240-55921217 SUBSTATION ENGINEERING PRODUCT REALISATION Work Instruction.pdf
- 240-57130114 Standard for Implementation of Substation Layouts for Transmission Substations.pdf
- 240-68970990 Standard for Auxiliary Transformers for Main Transmission Substations.pdf
- 240-68971742 Standard for Corona Studies.pdf
- 240-68971854 Standard for Power Frequency Electric and Magnetic Analysis in Substations.pdf
- 240-68971972 Standard for Stranded Flexible Conductor Selection.pdf
- 240-68972068 Standard For Tubular Conductor Selection.docx
- 240-68972170 Standard for Independent Power Producers Connections at Main Transmission Substations.pdf
- 240-147806256 Determination of Conductor Rating in Eskom.pdf
- 240-152844641 PHASE CONDUCTOR STANDARD FOR ESKOM OVERHEAD LINES.pdf
- 240-170000153 Copper Conductors Used for Earthing in Substations.pdf
- 240-171000066 TECHNICAL EVALUATION STANDARD FOR SUBSTATION TUBULAR CONDUCTORS - TX.pdf
- 240-171000067 SPECIFICATION FOR SUBSTATION TUBULAR CONDUCTOR - TX.pdf
- 979-1994 IEEE Guide for Substation Fire Protection.pdf
- 240-109589380 Direct Lightning Stroke Protection of Substations.pdf
- 240-114794277 Guideline for the Application of Intra-Span (Flying) Insulators.pdf
- 240-114967625 Operating Regulations for High Voltage Systems.pdf
- 240-116206790 Standard for Tertiary Bay Requirements when Power Transformers are used to Supply Station Auxiliary Loads and Rural Supplies.pdf
- 240-120804300 Standard For The Labelling Of Electrical Equipment within ESKOM Wires Networks.pdf
- 240-122922610 Specification for Substation Tubular Conductors.pdf
- CI summary - 240-103414344 Rev 5.pdf
- SAGC Network Version 9_July 2014.pdf
- SAGC Requirements for Renewable Power Plants Rev 2 8.pdf
- 240-68972308 Standard Procedure for Single Line Diagram Development.pdf
- 240-68972408 Standard for Flexible and Tubular Conductor Heights and Phase Spacing.pdf
- 240-68972746 Standard Template of Information Required for the Production of Substation Drawings.pdf
- 240-68972898 Standard for the Choice of Single and Three Mechanism Circuit-Breakers.pdf
- 240-122922610 Specification for Substation Tubular Conductors.pdf
- 240-128559117 Method Statements for Eskom Substations – Stringing , Erection, Earthing and Cabling.pdf
- 240-131732683 Functional Specification for a Smart Substation.pdf
- 240-134369472 Substation Earth Grid Design Standard.pdf
- 240-139282493 Security Lighting for Eskom Applications.pdf
- 240-146353995 Substation and Facility Maintenance.pdf
- 0.00-1286-0-0.pdf
- 0.00-1290-0-0.pdf
- 0.00-1310-0-0.pdf
- 0.00-5007.pdf
- 0.54-404.pdf
- 0.54-4316-0-4-.pdf
- 0.54-4319.pdf
- 0.54-4358-0-4.pdf
- 0.54-4658.pdf
- 0.54-4659.pdf
- 0.54-4713-1-5.pdf
- 0.54-4713-5-1.pdf
- 0.54-6106-1 NC9 mast.pdf
- 0.54-6106-2 NC9 mast.pdf
- 0.54-6106-3 NC9 mast.pdf
- 0.54-8739-0-0-.pdf
- 0.54-8805 SLP.pdf
- 0.54-8812 SLDB.pdf
- 0.54-393 earthing.rar
- 0.54-393 series 18.pdf
- 0.54-393-C1-6-.dgn.pdf
- 0.54-393-C2-5-.dgn.pdf
- 0.54-393-C3-5-.dgn.pdf
- 0.54-393-c3a-3-.dgn.pdf
- 0.54-393-c3b-2-.dgn.pdf
- 0.54-393-c4-3-.dgn.pdf
- 0.54-393-c5-4-.dgn.pdf
- 0.54-393-c6-1-.dgn.pdf
- 0.54-393-c6a-0-.dgn.pdf
- 0.54-393-c7-2-.dgn.pdf
- 0.54-393-c8-0-.dgn.pdf
- 0.54-393-c9-1-.dgn.pdf
- 0.54-393-c10-1-.dgn.pdf
- 0.54-393-c11-3-.dgn.pdf
- 0.54-393-c12-0-.dgn.pdf
- 0.54-393-c13-2-.dgn.pdf
- 0.54-393-c14-2-.dgn.pdf
- 0.54-393-c15-0-.dgn.pdf
- 0.54-393-c16-1-.dgn.pdf
- 0.54-393-c17-1-.dgn.pdf
- 0.54-393-c18-1-.dgn.pdf
- 0.54-393-c19-0-.dgn.pdf
- 0.54-393-c20-1-.dgn.pdf
- 0.54-393-c21-0-.dgn.pdf
- 0.54-393-c22-1-.dgn.pdf
- 0.54-393-c23-1-.dgn.pdf
- 0.54-393-c24-1-.dgn.pdf
- 0.54-393-c25-1-.dgn.pdf
- 0.54-393-c26-0-.dgn.pdf
- 0.54-393-c27-0-.dgn.pdf
- 0.54-393-c28-0-.dgn.pdf
- 0.54-393-c29-0-.dgn.pdf
- 0.54-393-c30-0-.dgn.pdf
- 0.54-393-c31-0-.dgn.pdf
- 0.54-393-C32-0-.dgn.pdf
- 0.54-393-T5 Rev 2.pdf
- 0.54-393-p1-2-.dgn.pdf
- 0.54-393-p2-2-.dgn.pdf
- 0.54-393-p3-0-.dgn.pdf
- 0.54-393-p4-0-.dgn.pdf
- 0.54-393-p5-1-.dgn.pdf
- 0.54-393-p6-0-.dgn.pdf
- 0.54-393-p7-0-.dgn.pdf
- 0.54-393-p8-0-.dgn.pdf
- 0.54-393-p9-0-.dgn.pdf
- 0.54-393-p10-0-.dgn.pdf
- 0.54-393-t1-2-.dgn.pdf
- 0.54-393-t2-2-.dgn.pdf
- 0.54-393-t3-2-.dgn.pdf
- 0.54-393-t4-2-.dgn.pdf
- 0.54-393-t5-1-.dgn.pdf
- 0.54-393-t6-1-.dgn.pdf
- 0.54-393-t7-1-.dgn.pdf
- 0.54-393-t8-1-.dgn.pdf
- 0.54-393-t9-2-.dgn.pdf
- 0.54-393-t10-1-.dgn.pdf
- 0.54-393-T11-0-.tif
- 0.54-393-t12-4-.dgn.pdf
- 0.54-393-t13-0-.dgn.pdf
- 0.54-393-T13A-0-.dgn.pdf
- 0.54-393-T14-0-.dgn.pdf
- 0.54-393-T14a-0-.dgn.pdf
- 0.54-393-T14b-0-.dgn.pdf
- 0.54-1150-100 Finishes spec notes.pdf
- 0.54-1150-101 Finishes schedule.pdf
- 0.54-1150-102 Doors.pdf
- 0.54-1150-103 Purpose made doors.pdf
- 0.54-1150-104 Windows.pdf
- 0.54-1150-105 Sanitaryware.pdf
- 0.54-1150-106 Burglar bars.pdf
- 0.54-1150-107 D1 drip.pdf
- 0.54-1150-108 Canopy.pdf
- 0.54-1150-109 Furniture.pdf
- 0.54-1150-110 Control building Concept plan.pdf
- 0.54-1150-111 Control building Concept GA.pdf
- 0.54-8808 DB1.pdf
- CONTROL BUILDING AIRCON AND VENTILATION.pdf
- CONTROL BUILDING LIGHTING AND POWER.pdf
- CONTROL BUILDING SCHEMATIC DB1.pdf
- FLOODLIGHTING SHT 1.pdf
- FLOODLIGHTING SHT2.pdf
- FLOODLIGHTING SHT3.pdf
- 0.53-2129-0-6.pdf
- 0.54-390sht79A.pdf
- 0.54-393-T18 Signed.pdf
- 0.54-393-T19 Signed.pdf
- 0.54-1150-25-12.pdf
- 0.54-1150-31-3.pdf
- 0.54-1150-76 Acid tank.pdf
- 0.54-5578-0 handrail.pdf
- 0.54-6140 watertankstand-steel.pdf
- 0.54-6622 - 2 rev 2.pdf
- 0.54-8732-0 Waveguide.pdf
- 0.54-10119 10m no post - Signed.pdf
- 0.54-8828-01 Rev 2.pdf
- 0.54-8828-02 Rev 1.pdf
- 0.54-8828-03 Rev 3.pdf
- 0.54-8828-04.pdf
- 0.54-8828-05.pdf
- 0.54-8828-06 Rev 1.pdf
- 0.54-8828-07.pdf
- 0.54-8828-08.pdf
- 0.54-8828-09.pdf
- 0.54-8828-10.pdf
- 0.54-8828-11.pdf
- 0.54-8828-12.pdf
- 0.54-8828-13 Maint. workshop store GA.pdf
- MAINTENANCE WORKSHOP ELECTRICAL.pdf
- SECURITY LIGHTING SHT 1.pdf
- SECURITY LIGHTING SHT 2.pdf
- 0.54-7515-1B rev 2 Corrected.pdf
- 0.54-7515-2-2.pdf
- 0.54-7515-3-2.pdf
- 0.54-7515-4-1.pdf
- 0.54-7515-5-0.pdf
- 0.54-7515-6-0.pdf
- 0.54-7515-7-1.pdf
- 0.54-7515-8-0.pdf
- 0.54-7515-9-0.pdf
- 0.54-7515-10-0.pdf
- 0.54-7515-11 ACB Concept GA.pdf
- ACCESS CONTROL BUILDING ELECTRICAL.pdf
- 0.54-4963-1-3-.pdf
- 0.54-4963-2-1-.pdf
- 0.54-4963-3-1-.pdf
- 0.54-4963-4-2-.pdf
- 0.54-4963-5-1-.pdf
- 0.54-314-0-2.pdf
- 0.54-8725-1-2.pdf
- 0.54-8725-2-0.pdf
- 240-76368574 - High Security Mesh fencing.pdf
- 0.54-5633-1-3.pdf
- 0.54-5633-2-1.pdf
- 0.54-5633-3-6.pdf
- 0.54-5633-4-1.pdf
- 0.54-398-1-13-.pdf
- 0.54-398-2-1-.pdf
- 0.54-7470-1-5-.pdf
- 0.54-7470-2-5-.pdf
- 0.54-7470-3-4-.pdf
- 0.54-7470-4-4-.pdf
- 0.54-7470-5-2-.pdf
- 0.54-7470-6-2-.pdf
- 0.54-7470-7-3-.pdf
- 0.54-7470-8-4-.pdf
- 0.54-7470-9-3-.pdf
- 0.54-7470-10-5-.pdf
- 0.54-7470-11-0-.pdf
- 0.54-401-0-8.pdf
- 0.54-710-0-7.pdf
- 0.54-1150-76 Acid tank.pdf
- 0.54-2089-0-6.pdf
- 0.54-3902 rev 2.pdf
- 0.54-3903.pdf
- 0.54-3904.pdf
- 0.54-3904-0.pdf
- 0.54-3905.pdf
- 0.54-3905-0.pdf
- 0.54-3906.pdf
- 0.54-3906-0.pdf
- 0.54-3989-0-5-.pdf
- 0.54-3996-0-11--Default-000.pdf
- 0.54-4169-0-7.pdf
- 0.54-4316-0-4-.pdf
- 0.54-4316-0-5.pdf
- 0.54-4319-0-Default-000.pdf
- 0.54-4358-0-3.pdf
- 0.54-4358-0-4.pdf
- 0.54-4368-0-3-.pdf
- 0.54-4659-0-9.pdf
- 0.54-4726-0-10-Default-000.pdf
- 0.54-5588-1-Default-000.pdf
- 0.54-5588-2-Default-000.pdf
- 0.54-5588-3-Default-000.pdf
- 0.54-5588-4-Default-000.pdf
- 0.54-6140 watertankstand-steel.pdf
- 0.54-7511-0-3-.pdf
- 0.54-7512-0-0-.pdf
- 0.54-7514-0-1-.pdf
- 0.54-7515-1 rev 6.pdf
- 0.54-7515-2-2.pdf
- 0.54-7515-3-2.pdf
- 0.54-7515-4-1.pdf
- 0.54-7515-5-0.pdf
- 0.54-7515-6-0.pdf
- 0.54-7515-7-1.pdf
- 0.54-7515-8-0.pdf
- 0.54-7515-9-0.pdf
- 0.54-7515-10-0.pdf
- 0.54-8280-0-2-.pdf
- 0.54-8293-0-0-.pdf
- 0.54-8723-Default-000.pdf
- 0.54-301-0-3.pdf
- 0.54-301-3.pdf
- 0.54-302-0-3.pdf
- 0.54-302-0-3-Default-000.pdf
- 0.54-303-0-3.pdf
- 0.54-305-0-3.pdf
- 0.54-306-0.pdf
- 0.54-306-0-6.pdf
- 0.54-306-0-7.pdf
- 0.54-307-0.pdf
- 0.54-307-0-5.pdf
- 0.54-309-0-2.pdf
- 0.54-309-0-2-.pdf
- 0.54-311-0-1-.pdf
- 0.54-314-0-2.pdf
- 0.54-315-0-6--Default-000.pdf
- 0.54-336-0.pdf
- 0.54-336-0-4.pdf
- 0.54-337-0-6-.pdf
- 0.54-338-0-1-.pdf
- 0.54-400-1-5.pdf
- 0.54-400-2-0--Default-000.pdf
- 0.54-403-0.pdf
- 0.54-673-0-5-.pdf
- 0.54-779-0-6-.pdf
- 0.54-1794-3.pdf
- 0.54-2088-0_0-Default-000.pdf
- 0.54-3512-1-5-.pdf
- 0.54-3512-2-Default-000.pdf
- 0.54-3531-0-3.pdf
- 0.54-3532-0-4-.pdf
- 0.54-3533-0-4-.pdf
- 0.54-3776-0-1.pdf
- 0.54-3901.pdf
- 0.54-3902 rev 2.pdf
- 0.54-3909.pdf
- 0.54-3909-0.pdf
- 0.54-3910.pdf
- 0.54-3910-0.pdf
- 0.54-3911.pdf
- 0.54-3926-0-1.pdf
- 0.54-3927 rev 0.pdf
- 0.54-3989-0-5-.pdf
- 0.54-4282-0-0-.pdf
- 0.54-4320-0-7.pdf
- 0.54-4337-0-1-.pdf
- 0.54-4658-0-4-.pdf
- 0.54-4721-0.pdf
- 0.54-4721-0-Default-000.pdf
- 0.54-4722.pdf
- 0.54-6106-3-Default-000.pdf
- 0.54-6140.pdf
- 0.54-6326-0-2-.pdf
- 0.54-6434.pdf
- 0.54-6603.dgn.pdf
- 0.54-6603-Default.pdf
- 0.54-6609-0-1.pdf
- 0.54-6613-0-2-.pdf
- 0.54-8739-0-2-.pdf
- 0.54-10101.pdf
- 0.54-10103.pdf
- 0.54-10104.pdf
- 0.54-10105.pdf
- 0.54-10106.pdf
- 0.54-10112-0-1.pdf
- 0.54-390-00-0-COMBINED.pdf
- 0.54-6597-0-2- security fences layout.pdf
- 240-77297024 Standard for the Operating Diagrams for ESKOM Transmission Substations.pdf
- 240-82736997 Stringing, Cabling, Earthing, and Erection Specification for Transmission Substations.pdf
- 240-83534936 Tubular and Stranded Conductor Clamps Additional to The Existing Standards.pdf
- 240-83563472 Drawing Standard for Substations - Power Plant.pdf
- 240-84854974 Continuity Measurement of Substation Earth Grid Systems.pdf
- 240-85524358 Standard For Determining Busbar Conductor Short - Circuit Forces And Phase Conductor Displacement In Outdoor Substations.pdf
- 240-85524376 Standard For Determining Dropper Conductor Short Circuit Forces on Equipment In Outdoor Substations.pdf
- C0 ECC3 Contract cover page Mercury 3rd Transformer- EPC.doc
- C1 1 ECC3 Offer Acceptance Mercury 3rd Transformer 1.doc
- C1 2a ECC3 Data by Employer Mercury 3rd Transformer- EPC.doc
- C1 2b ECC3 Data by Contractor Mercury 3rd Transformer - EPC.doc
- C1 3 ECC3 Proforma Guarantees Mercury 3rd Transformer EPC.doc
- C2 ECC3 Pricing Data Option A Mercury 3rd Tranformer EPC.doc
- C3 1 ECC3 Employers Works Information Mercury 3rd Tranformer EPC Rev 2- stability.doc
- C4 ECC3 Site Information Mercury.doc
- Project Stability Scope for Mercury 3rd 500MVA TRFR Project.pdf
- 1.Mercury Substation - 3nd Transformer Project - Activity Schedule.xlsx
- Appendix - TPD Contractor Evaluation Tool Rev 16_excel.xls
- Invitation to tender Two Envelope System 12Oct2023 (002) (005) 2024.04.24.pdf
- SDL&L objectives.docx
- 202211 Tender Returnable Documents for EPC EPCM or Owner's Engineer_TPDMAN-FM-203_Rev2 (1).docx
- 202211 Tender Returnable Documents for EPC EPCM or Owner's Engineer_TPDMAN-FM-203_Rev2 (1).xlsx
- 20240229_Internal EMP letter Mercury 500MVA Trfr 3 (002).pdf
- 20240401_Generic EMPr - Mercury Substation (003).pdf
- Eskom Transmission Waste Management Plan 2023_2028.pdf
- Eskom Waste Management Standard.pdf
- Eskom's (SHEQ) Policy poster (32-727) 17 October 2023 - REV 7.pdf
- 20230711_(Form A) Tender Contract SHEQS Requirements For EPC Contractor_TPDMAN-FM-157_Rev2.docx
- 20230713_Supplier Quality Management List of Tender Returnables Documents (EPC)_TPDMAN-FM-219_Rev 1 _.xlsx
- 20230713_Supplier Quality Management List of Tender Returnables Documents_EPC_TPDMAN-FM-219_Rev 1.pdf
- 20230907_Quality Plan_Mercury MTS Expedited IPP Program- Mercury 3rd 400 132 kV transformer_TPDSOU-131_Rev 1 NMM.pdf
- 32-37 Substance Abuse rev3.pdf
- 32-95 Occupational Health and Safety Management Procedure Rev8.pdf
- 32-136 Contractor Health and Safety Requirements rev4.pdf
- 32-418 Working at Height Standard rev3.pdf
- 32-520 Occupational Health and Safety Risk Assessment Procedure Rev 3.pdf
- 32-1126 Smoking Policy Rev 1.pdf
- 240 43848327 Employees' right of refusal to work in unsafe situations procedure rev1.pdf
- 240 62196227 Eskom life-saving rules rev6.pdf
- 240 62946386 Vehicle and Driver Safety Management rev6.pdf
- 240 100979499 Personal Protective Equipment for Work at Heights Specification rev1.pdf
- 240-120054284 Eskom Personal Protective Equipment rev1.pdf
- 2019-20-05 PDP Occupational Hygiene Guideline.pdf
- 20200917_Requirement Letter for Construction Professional Registration_Rev0.pdf
- 20230420_Annexure B_ SHE Acknowldgement Form_240-77471499_Revised.pdf
- 20230720_Annexure C2 - Medium Risk_Evaluation_240-77471969.docx
- 20230920_TPD_Health Safety Specification (HS Spec)_Mercury SS_Rev5_AS.pdf
- BaseLine Risk Assesment_Civil Works_Mercury SS.xlsx
- Eskom's (SHEQ) Policy poster (32-727) 17 October 2023 - REV 7.pdf
Save to Calendar
- Save closing date to your Google/Outlook/Yahoo/Other Calendar
- Save inspection date to your Google/Outlook/Yahoo/Other Calendar
Share This Tender
Get Access to Awarded Tenders & Awarded Companies
Awarded Tenders: Useful for understanding pricing trends, identifying potential partners, and tracking the performance of specific vendors, among other use cases
Awarded Companies: Track who is winning tenders and what kinds of bids are successful. This information is invaluable for competitive analysis and for identifying potential partners or competitors.
(New) Say Goodbye to Tender Chaos
Struggling with missed deadlines and disorganized tenders? Our upcoming suite of products is designed to streamline your tender management. Join our waitlist to be the first to experience the change.